Work on the Crib Groyne will commence on the 13th January 2020 and is scheduled to be completed before the 5th March 2020.

 

Invitations to tender on the removal of the stockpile and the Stilling Lagoon will be released next week.

 

The dredging of the harbour entrance will also be scheduled for March 2020.

 

We met with Royal Smalls before Christmas and are awaiting their response to using a Cutter Suction dredger at the harbour entrance for future dredging campaigns.

 

We will update you as these matters progress.